What a lender should check before releasing a construction payment

October 2026 · 3 min read · De Consulting

Aerial view of central Tirana

Every drawdown request comes with a payment application and a progress report from the borrower. Before the bank releases the money, an independent monitor answers one question: is the money left enough to finish the project? These are the six checks behind that answer.

1. Is the work really there?

Visit the site and compare what is built with what is claimed. Check measured quantities against the bill of quantities and the drawings, and photograph the evidence. Materials on site should only be paid for if they are protected, stored and owned by the project.

2. Does the budget still hold?

Compare the anticipated final cost with the approved budget. Add pending variations and claims, not only approved ones. Then run the funding test: the remaining loan plus the remaining equity must cover the cost to complete.

3. Is the programme realistic?

Compare actual progress with the baseline programme. A slipping completion date means more interest, possible covenant breaches and income that starts later. If the critical path is late, ask for the contractor's recovery plan.

4. Are the contract terms respected?

Check that retention is being held, advance payments are being recovered and certified amounts follow the contract. Under FIDIC, the Engineer's payment certificate should match the amount requested.

5. Are permits, insurance and safety in order?

The building permit and its conditions must cover what is being built, insurance must be in force, and there should be no suspension orders or serious safety breaches.

6. Did earlier payments reach the right people?

Ask for evidence that previous drawdowns paid the contractor, and that the contractor is paying its subcontractors and suppliers. Unpaid suppliers are an early warning of trouble.

The monitor's report should end with a clear recommendation: release in full, release in part with conditions, or hold. A good report is short, uses photographs and numbers, and arrives before the drawdown date, not after.

For banks and funds, we provide independent cost and progress monitoring on projects across Albania, reported monthly in English.

Talk to us

Have a project in Albania?

Start with a 30-minute call. We reply within one working day, in English, Albanian or Italian.

Book a 30-minute call

More insights

Green hills above a bay on the Albanian coast

Cost control

3 mistakes that push tourism projects over budget

Read article
Hand marking up construction drawings

Digital delivery

Procore on Albanian projects: one system instead of a hundred emails

Read article
Highway interchange through green plains, aerial view

Project controls

Earned value in plain words: knowing a project is late before the contractor says so

Read article